Governor Abbott orders mandatory reviews of new data center projects as interconnection queue balloons to 474 gigawatts, raising concerns about the state's power grid capacity.
TechCrunch — AI
Governor Greg Abbott has made data center development a regulatory priority, announcing that all new projects in Texas will now require audits from both the state's Public Utility Commission (PUCT) and its grid operator, the Electric Reliability Council of Texas (ERCOT).
The move reflects mounting pressure on Texas's electricity infrastructure. The sheer volume of proposed data center construction has created a backlog of grid connection requests that threatens to strain the system beyond safe operating limits.
Growth of the interconnection queue#
Texas's grid connection queue has swelled dramatically in recent months. At the start of the year, ERCOT was tracking 233 gigawatts of projects seeking grid access. By mid-2026, that figure had more than doubled—ERCOT now reports 474 gigawatts in pending requests, with roughly 90% stemming from data center developers.
To put this in perspective, the current queue represents more than five times ERCOT's total peak demand. While many of these projects remain in early planning stages—developers often file to secure their place in line even if they later abandon proposals—the sheer number indicates a potential collision between ambition and physical capacity.
Why Texas became the target#
Data center operators have flocked to Texas for good reason. The state offers loose regulatory frameworks, abundant natural gas reserves, and historically low electricity costs. Only Virginia hosts more data centers than Texas across the nation.
Renewable energy has supported growth on the grid: utility-scale solar capacity quadrupled between 2021 and 2025, and wind power has helped ERCOT manage demand. Yet this trajectory is shifting. Rising demand from data centers and cryptocurrency facilities has begun pushing electricity prices upward, a trend Abbott appears determined to reverse.
The audit mandate and compliance push#
Under the new directive, ERCOT and PUCT will examine proposed data centers on multiple fronts: electricity demand (both on-site and indirect consumption), water usage, noise mitigation, lighting controls, tax incentive claims, and ownership structures.
This represents a marked shift for a state renowned for minimal regulation—Houston infamously lacks a comprehensive zoning code. Abbott had previously attempted a voluntary information-gathering survey, but most data center operators declined to participate. The audit requirement now forces the issue.